Distribution Transformers for the Philippines

Overhead and pad-mounted distribution transformers built for the Philippine grid at 60 Hz: 13.2, 13.8 and 34.5 kV primary, with 230 V, 254/440 V and 480 V secondaries. Single-phase pole-mounted units and three-phase substation units are both within our range.

Local network data

Distribution voltages7.62/13.2 kV, 8/13.8 kV, 20/34.5 kV
System frequency60 Hz
Secondary voltage230 V; 254/440 V; 480 V where specified
Pole-mounted range15 – 333 kVA, single phase
Cooling TypeONAN on oil-immersed builds; AN / AF on dry-type builds
Local practiceANSI / IEEE C57.12 distribution practice
Design basisIEC 60076 and ANSI C57 as applicable to the order
EnvironmentTropical, high humidity, coastal and typhoon exposure

Everything for the Philippines is built and factory-tested at 60 Hz.

Coastal and typhoon exposure drives the enclosure, corrosion protection and fitting spec — tell us the site and we build to it.

Build specification

PhaseThree-phase
Cooling TypeONAN on oil-immersed builds; AN / AF on dry-type builds
Core MaterialHigh-efficiency (CRGO) silicon steel
Connection GroupDyn11, Yyn0, Dyn5
Winding MaterialCopper / Aluminium
Tap Changer± 2 × 2.5% Off-Circuit Tap Changer (OCTC)
Noise Level≤ 60 dB at 1 meter
EnclosureHermetically sealed steel tank, weatherproof for indoor and outdoor use
Altitude≤ 1,000 m or customized
Ambient Temperature Range-30 °C to +50 °C
Standards ComplianceDesigned to comply with IEC 60076, IEEE C57 and ANSI C57 as applicable to the order
WarrantyTwo years
Delivery TimeTypically 30 days, depending on quantity
Min. order quantity≥ 1 set

Oil immersed or cast resin?

Where these units are used

Questions buyers ask

Yes. Philippine units are wound and factory-tested at 60 Hz, and the test report states the test frequency.
Yes — single-phase pole-mounted units from 15 to 333 kVA sit inside our distribution range, alongside three-phase pad-mounted and substation units.
We build to IEC 60076 and ANSI C57 as applicable to the order. Tell us what the utility or the cooperative specifies and we match it.
Rating, primary and secondary voltage, frequency, vector group, quantity, application and the site conditions.

Send us the specification

Rating, primary and secondary voltage, frequency, quantity and the application. We answer within one working day.

Scroll to Top